The Ministry of Industry decides to increase electricity production by 650 megawatts

The Minister in charge of the Ministry of Industry, Mines and Energy, Salah Al-Zawari, announced on Sunday the approval of a package of measures to increase the production capacity of electricity by about 650 megawatts to secure supply during 2027. This came during a joint public meeting of the Assembly of the Representatives of the People and the National Council of Authorities and Territories to discuss the Ministry's budget for 2027.
The technical plan includes adding 150 megawatts by concentrating existing turbine cooling systems, integrating 300 megawatts of renewable energy, as well as concentrating 200 megawatts gas engines. The ministry is considering increasing the additional capacity from renewable energy projects to 500 megawatts by accompanying investors and accelerating the completion co-ordination to enter production starting in February 2027.
The visitor said that the Tunisian electricity and gas company had restored the turbine at Turomari to service to restore its production capacity of 300 MW. The minister said that a contractor has been appointed to concentrate a third turbine within major projects worth over 600 million dinars, to provide more than 300 megawatts of additional power before the year 2028.
For the first time, the ministry is aiming to integrate an electricity storage system with a total capacity of 300 megawatts, distributing a balance between pre-2027 and the end of the same year, while exploring the possibility of accelerating the completion of full capacity before next summer. The state aims to increase the share of renewable energy from 9% now to 16% in 2027, up to 35% by 2030.
The measures also include the implementation of a programme to control electricity consumption during peak hours by negotiating with high-consumption medium voltage enterprises to adjust the pace of their consumption, and the provision of differential tariffs to incentivise craftsmen to turn part of their activity into low-cost periods, along with accelerating the exploitation of gas and oil fields to reduce supply costs and energy deficit.